MVSA
This project consist of 4 buildings. Bldgs 1 through 3 are 1 story below grade parking garage with 2 story concrete podium above parking garage. Bldg 4 is ground level footings and slab on grade.
Status : Awarded
Scope
Furnish & install shoring & lagging, mass excavation, dewatering, waterproofing, rat slab, mat foundation, suspended PT decks, concrete columns & walls, formwork, reinforcement, ready mix.
Elevated Decks : 2 Levels
Reinforcing Weight : 5,380,555 lbs
Volume of Concrete : 44,872 cy
Location : Mountain View, Ca
Sq. Footage : 680,000 SqFt
Construction Duration : 11 Months
Owner : Greystar
General Contractor : Greystar
Architect : Seidel Architects
Structural Engineer (Concrete) : KPFF Engineers
Reinforcing Contractor : RJS & Associates. Inc.
Concrete Placer : RJS & Associates. Inc.
False Work Contractor : RJS & Associates. Inc.