Bush Street SF
1 story below grade parking garage with 1 story concrete podium above parking garage.
Status : Complete
Scope
Furnish & install footings, SOG, suspended PT decks, concrete columns & walls, formwork, reinforcement, ready mix.
Elevated Decks : 1 Levels
Reinforcing Weight: 469,595 lbs
Volume of Concrete: 3,542 cy
Location : Santa Clara, Ca
Sq. Footage : 68,380 SqFt
Construction Duration: 6 Months
Owner: Thompson Dorfman Partners
General Contractor: Building Group Inc.
Architect : KTGY
Structural Engineer: FBA Engineers
Reinforcing Contractor : RJS & Associates. Inc.
Concrete Placer : RJS & Associates. Inc.
False Work Contractor : RJS & Associates. Inc.