Monticello

1 story below grade parking garage with 1 story concrete podium above parking garage.

Status : Complete

Scope

Furnish & install footings, SOG, suspended PT decks, concrete columns & walls, formwork, reinforcement, ready mix. 

Elevated Decks : 1 Levels

Reinforcing Weight: 9,047,044 lbs

Volume of Concrete: 89,526 cy

Location : Santa Clara, Ca

Sq. Footage : 897,014 SqFt

Construction Duration: 12 Months

Owner: Irvine Company

General Contractor: Western National Contractor

Architect: McLarand Vasquez Emsiek & Partners

Structural Engineer: FBA Engineers

Reinforcing Contractor : RJS & Associates. Inc.

Concrete Placer : RJS & Associates. Inc.

False Work Contractor : RJS & Associates. Inc.